★★★★★ 5 Star Rated 15+ Years Estimating $1M PI Insurance No Lock-In Contracts Australia-Wide · Fully Remote
(08) 6156 9550eagle_enquiries@outlook.com
Home All Services How It Works Pricing Calculator Blog About FAQ Service Areas

Concrete

Concrete Estimating Decorative Concrete Brick Paving

Trades

Earthworks Estimating Bricklaying Estimating Carpentry Estimating Plumbing Estimating Electrical Estimating Roofing Estimating Civil Estimating Landscaping Estimating Termite Treatment

Finishes & Linings

Plastering Estimating Painting Estimating Tiling Estimating Waterproofing Estimating Ceilings Estimating Insulation Estimating Texture Coating Blinds Estimating

Deliverables

Quantity Takeoff & BOQ Construction Programs Progress Claims & Variations Sub-Contract Reviews Residential Estimating Commercial Estimating Industrial Estimating Get a Quote
Trades · Australia-Wide

Roofing Estimating & Roof Area Takeoffs

True roof area worked from the pitch, not the plan view. Sheets cut to length, tiles counted, and every metre of ridge, valley, barge, gutter and flashing measured on its own line.

15+
Years Estimating
20+
Trades Covered
24hr
Turnaround
$1M
PI Insurance
Free
First Estimate
✓ First estimate free
✓ 24hr turnaround on most residential jobs
✓ $1M professional indemnity cover
✓ No lock-in contracts
✓ Tax deductible
Why It Is Different

True area, measured off the pitch

A roof measured in plan view is always smaller than the roof you have to cover. At 22.5 degrees you are about eight per cent short; at 30 degrees around fifteen. On a big roof that is a real quantity of material and a real hole in the quote.

We take the pitch off the elevations, convert every plane to its true area, and then measure the linear items separately — because on most roofs the flashing, gutter and capping metres carry as much labour as the sheeting does.

The Scope

What we do on a roofing job

Each roof plane is measured individually and converted to true area using its pitch. Hips, valleys and ridges are measured to their true lengths, which are longer again than either the plan length or the rafter length.

For metal roofing we produce a sheet schedule: cut lengths by run, with the profile and finish from the specification, plus fixings, closures and sarking area. Standard-length ordering versus cut-to-length is called out, since it changes both waste and lead time.

For tile roofing we count tiles by type, including ridge and hip tiles by the metre, plus bedding and pointing, sarking, battens and valley irons. Either way, gutter, fascia, downpipes, flashings and penetrations are measured as their own lines.

Line By Line

Every item measured, and why it matters

Nothing here is an allowance. Each line is measured off your drawings in its own unit, so you can check it against the plan yourself.

What a roofing estimate covers
ItemHow it is measuredWhy it matters
True roof areaEach plane measured and converted from plan area using its pitchThis one conversion is the difference between a right quote and a short one
Sheets or tilesSheet cut lengths by run, or tile counts by type, plus wasteA sheet schedule lets you order cut-to-length instead of paying for offcuts
Ridge and hipTrue linear metres, with capping or ridge tiles and beddingHip and ridge metres are longer than they look in plan, on every roof
ValleysTrue linear metres, plus valley irons or gutters and sarkingValleys are slow, detailed work and belong on their own line
Barge and fasciaLinear metres by profileEasy to measure, easy to forget, and always visible when it is missing
Gutter and downpipesGutter metres by profile, downpipe count and drop lengthsDownpipe lengths come off the elevations, not the roof plan
FlashingsLinear metres by type — apron, step, sill, wall and parapetFlashing metres are labour-heavy relative to their material cost
PenetrationsCounted individually: vents, whirlybirds, skylights, flues, solarEach one is a detail, a flashing and a labour item
Safety and accessEdge protection metres, scaffold and roof anchor requirementsA code requirement with real cost, and never inside a per-square-metre rate
The Detail

How pitch changes the area you have to cover

How pitch changes the area you have to cover
PitchApproximate factor on plan areaEffect
15°About 1.04Roughly 4% more material than the plan suggests
22.5°About 1.08Roughly 8% more — the common metal roof pitch
25°About 1.10Around 10% more
30°About 1.15Around 15% more — common on tiled roofs
35°About 1.22Over 20% more, plus slower and less safe access
45°About 1.41Over 40% more, and effectively a different job to install

Waste depends on the shape, not the size

A simple gable roof cuts almost no waste on sheeting. A hipped roof with three valleys and a dormer cuts a lot, because every sheet meeting a hip or valley is a raking cut. We set the waste allowance from the roof geometry rather than applying a flat percentage.

Tiles behave the same way. Cutting into valleys and around penetrations breaks tiles, so the allowance goes up on a cut-up roof and stays low on a straightforward one.

How It Works

From your plans to a priced spreadsheet

The same five steps on every job, whether it is a single slab or a full tender package.

  1. Send us the plans

    Email the architectural and structural drawings, the specification and the scope of works in whatever format you have — PDF, DWG, or photos of a marked-up set. If something is missing we will tell you before we start, not after.

  2. We measure the roofing scope

    Each roof plane is measured individually and converted to true area using its pitch. Hips, valleys and ridges are measured to their true lengths, which are longer again than either the plan length or the rafter length.

  3. Colour-coded markup you can actually check

    Every measured item gets its own colour and legend entry on the drawing. When the takeoff comes back you can see exactly what was counted and what was not, so you are never asked to trust a number you cannot trace. This is the part clients tell us they did not know they needed until they had it.

  4. A live Excel sheet with your own rates in it

    The takeoff is delivered as a working spreadsheet, not a locked PDF. Your rates sit in their own column, so you can change a supply price or a labour rate and watch the total move. Plug in your own numbers and the sheet is yours to reuse on the next job.

  5. Cross-check, then deliver

    Quantities are re-measured independently and cross-checked against the drawing before anything leaves here. You get the marked-up plans, the priced spreadsheet and a plain-English note on anything we flagged as unclear or excluded.

You keep the working file

The takeoff arrives as a live Excel spreadsheet with the colour-coded marked-up plans beside it. Your rates go in your own column, so you can plug in your own supply and labour numbers and reuse the sheet on the next job. Nothing is locked.

What it costs

First estimate free. After that the fee is confirmed in writing as a fixed amount before any work starts. No retainer, no subscription, no lock-in contract. Full pricing detail here →

Typical Work

Roofing we price every week

Wind, corrosion and the fixing schedule

Wind classification changes the fixing schedule, and the fixing schedule changes both the screw count and the labour. A coastal or high-wind site can carry substantially more fixings per square metre than a sheltered one.

Coastal exposure also drives the material specification — the corrosion environment decides which coating or substrate is acceptable, and the difference in supply price is significant. We work to the specified product rather than the cheapest equivalent, and note where the spec leaves it open.

Standards

What we measure against

Quantities are measured against the standards and the specification for your job. Where a drawing and a standard disagree, we flag it rather than quietly picking one.

Australian Standards referenced on roofing work
StandardCoversRelevance
AS 1562Design and installation of sheet roof and wall claddingMetal roofing installation
AS 2050Installation of roof tilesTile fixing and flashing requirements
AS/NZS 3500.3Plumbing and drainage — stormwater drainageGutter and downpipe sizing
AS 4055Wind loads for housingFixing schedule and wind classification
Costly Mistakes

Where roofing quotes usually go wrong

None of these are unusual. They are the things that get missed when a quote is put together at 9pm after a full day on the tools.

FAQ

Roofing estimating questions

If your question is not here, email it through and you will get a straight answer, not a sales call.

Each roof plane is measured in plan and then converted using its pitch, taken off the elevations or the sections. Hips, valleys and ridges are measured to their true lengths separately.

The marked-up drawings show each plane with its own colour and its own area, so you can check the total against the roof before you order.

Yes — cut lengths by run, with the profile and finish from the specification, plus fixings, closures and sarking. That lets you order cut-to-length rather than paying for offcuts, which on a large roof is a meaningful saving.

Yes. Tile counts by type with waste, ridge and hip tiles by the metre, bedding and pointing, sarking, battens and valley irons. Concrete and terracotta are priced as specified rather than interchangeably.

All of them, each on its own line. Gutter and fascia by the metre by profile, downpipes counted with their drop lengths off the elevations, and flashings by type. On many roofs the linear items carry as much labour as the sheeting.

Edge protection metres, scaffold and any roof anchor requirements are listed as separate items with the extent they cover. They are a legal requirement and a real cost, and they never belong inside a square metre rate.

A roof plan, the elevations and the sections, plus the specification for the profile, finish and fixing requirements. If there is no roof plan we can work from the architectural set, and we will note the pitch we have used so you can confirm it.

Most residential roofs come back within 24 hours of the plans arriving. Large commercial or industrial roofs take longer because there are more planes and more detail — we confirm the timing before starting.

Related

Other trades and deliverables

Most jobs cross more than one trade. We can price the whole package in one spreadsheet.

See all 20+ trades we estimate →

Send through your roofing plans

Your first estimate is free. Email the drawings and the scope, and you will have a marked-up takeoff and a priced spreadsheet back within 24 hours on most residential jobs. Prefer to talk first? Reply with "KEEN" and your number.

Get My Free Estimate →